Concrete Calculator: Pour Planner & Strength Gain
Calculate concrete volume, whole bags, ready-mix orders and rebar grids. Estimate daily strength gain at the curing temperature and dates for your strength targets.
Use this concrete calculator to plan a pour and see how curing temperature changes the expected strength timeline. It combines a material takeoff with a strength forecast for engineers, students, site planners, and homeowners preparing a small project.
Choose a slab, rectangular footing, circular column, or solid staircase. Enter the finished dimensions and the number of identical elements. A footing is treated as a rectangular prism; a staircase is a solid stack of equal rises and treads, without a landing. The tool separates the geometric volume from your extra allowance for uneven ground, handling losses, and uncertainty.
For ready-mix, set the supplier's ordering increment and usable delivery capacity. The order rounds up to the next increment, and delivery loads round up to whole loads. For bagged concrete, choose a published 80 lb or 60 lb yield, or enter the yield printed on your own bag. The result answers how many bags of concrete to buy by rounding up after adding the allowance. Yields are approximate; bag weight by itself does not determine yield.
A rectangular rebar grid can be included for slabs and footings. Enter clear cover, bar diameter, maximum centre spacing, and the number of grid mats. The takeoff counts a bar at each boundary, adjusts spacing down to fit, and totals straight cut lengths and theoretical steel mass. It excludes laps, hooks, chairs, ties, anchorage, and cutting optimisation. It does not design reinforcement or check structural capacity.
For the strength forecast, enter the expected mean 28-day compressive strength at 20 °C, the cement development class, and the average concrete temperature throughout curing. The temperature is the concrete's temperature, which can differ greatly from the air. The maturity calculation converts calendar time into equivalent days at 20 °C. The chart and daily table show the resulting strength estimate alongside the reference-temperature curve. Press play on the age input to move through the timeline.
Concrete curing time temperature effects depend on the actual mix and moisture supply. Predictions begin at one equivalent day and stop increasing at the entered 28-day strength. Form-release and vehicle-access targets are editable planning thresholds, not prescribed safe values. An engineer must select appropriate targets and approve loading or form removal using project-specific strength tests or calibrated maturity monitoring. Keep concrete moist and follow the mix supplier's curing instructions; this planner does not model freezing, drying, heat generation, or changes in ultimate strength.
How it is calculated
Concrete volume and supply
For slabs and rectangular footings, . Circular columns use . A solid staircase is the sum of stacked tread prisms: . Multiply by the number of identical elements. Add the user allowance, then independently round ready-mix up to the supplier's increment or bags up to whole bags. Delivery count uses the rounded ready-mix order. QUIKRETE training, attached s2 page 11, supplies the 0.60 ft³ and 0.45 ft³ bag yields. The rounding subtraction of removes floating-point noise at exact integer boundaries.
Rectangular reinforcement takeoff
The supplied cover is clear cover to the outside of the steel. The outer bar centre spans are and . Bars parallel to L number , with at least two; interchange L and W for the other direction. Equal spacing fits between the boundary bars. Straight cut lengths are and . Multiply by mats and identical elements. Theoretical mass uses with nominal steel density 7850 kg/m³. These geometry and mass equations are derived here, not a reinforcement design rule.
Temperature and strength
Use the constant-concrete-temperature Arrhenius equivalent-age method described by FHWA-HIF-07-004 (attached s1 pages 2–3), with the fib Model Code 2010 benchmark : , . This normalises the reference precisely to 20 °C using 273.15 rather than the rounded 273 and 13.65 constants. It uses the fib benchmark, not FHWA's alternative temperature-dependent activation-energy correlation.
The EN 1992-1-1:2004, clause 3.1.2 / fib Model Code 2010 development function is . CEM I benchmarks are s = 0.20 (42.5 R, 52.5 N/R), 0.25 (32.5 R, 42.5 N), and 0.38 (32.5 N), as reported in Vollpracht et al. 2018, attached s3 page 4; equivalent-age basis is on page 24. This planner withholds results below one equivalent day and caps the ratio at 1 above 28 equivalent days. For a target fraction , inverse age is ; divide by for calendar days.
Assumptions
One uniform shape per run; repeated elements are identical. Slabs and footings are rectangular prisms, columns are solid circles, and steps have a solid underside, equal treads/rises and no landing. Concrete volume does not subtract reinforcement displacement. The default 10% concrete and 5% steel allowances are editable planning choices, not standard requirements.
Bag yield defaults refer to the cited product; they do not specify its strength coefficient. The entered mean 28-day strength and strength targets must share the same test basis. Characteristic design strength must not be substituted for mean strength without justification. Moisture remains sufficient for hydration. Concrete temperature is uniform and constant throughout the curing period; air temperature is only a rough proxy when verified to be representative.
A rectangular grid mat contains two crossing bar sets. Mat fit checks cover geometric occupancy only. Steel purchasing allowance is not a splice design or a stock-bar cutting schedule. Defaults for form release (15 MPa) and vehicle access (25 MPa) are illustrative user targets, not universal requirements.
Where it applies
Quantity planning and educational strength estimates only. Nominal CEM I concrete, entered mean strength 10–60 MPa, average concrete temperature 5–35 °C, calendar horizon 1–56 days, and strength-model equivalent age 1–28 days. The source study specifically cautions against predictions before 24 equivalent hours (s3 page 5). Curves contain intentional gaps below this limit; beyond 28 equivalent days they plateau at the entered reference strength. Blended binders, retarders, accelerators and unfamiliar mixes need test-calibrated parameters; changing s alone does not calibrate temperature sensitivity.
The constant-temperature forecast is not an ASTM C1074 calibrated field maturity assessment. It omits hydration heat, temperature history, moisture loss, freezing, consolidation defects and early-temperature effects on ultimate strength. FHWA requires mix-specific calibration and verification (s1 pages 2–4). Form removal, shoring changes and vehicle loading require approval by the responsible engineer using appropriate in-place strength evidence and capacity/load checks. Reaching a target in this forecast is not permission to strip forms or drive on concrete. Continue curing according to the project requirements and supplier instructions. Check against the standard in force and local project specifications; the cited strength-development formulation follows the stated older edition, not an assertion of compliance with EN 1992-1-1:2023.
References
- FHWA, Maturity Testing for Concrete Pavement Applications, FHWA-HIF-07-004 (2006), pp. 2–4. https://www.fhwa.dot.gov/pavement/pccp/pubs/06004/06004.pdf
- Vollpracht, Soutsos and Kanavaris (2018), Strength development of GGBS and fly ash concretes and applicability of fib model code’s maturity function – A critical review. DOI: 10.1016/j.conbuildmat.2017.12.054. Open author manuscript: https://pureadmin.qub.ac.uk/ws/files/139140883/JCBM_FIB_MC_strength_development_Accepted_manuscript.pdf
- QUIKRETE, Mixing & Placing Concrete & Cement Mixes, Training Module 3, slide 11. https://www.quikrete.com/dealers/training/presentations/3-mixing-placing-concrete-cement-mixes-training.pdf
- EN 1992-1-1:2004, clause 3.1.2; fib Model Code for Concrete Structures 2010 (2013 publication), strength-development and equivalent-age methods. Refer to the standards in force for project design.
Inputs
| Input | Symbol | Unit | Default |
|---|---|---|---|
| Pour shape One shape per calculation; repeat for mixed pours. | shape | Slab | |
| Identical elements Multiplies volume and rectangular grid quantities. | n_items | 1 | |
| Length Finished length of each slab or footing. | L | m | 6 |
| Width Finished width of each rectangular element or staircase. | W | m | 4 |
| Depth / thickness Uniform finished thickness. | h | m | 0.15 |
| Column diameter Solid circular cross-section. | D_col | m | 0.4 |
| Column height Finished concrete height. | H_col | m | 3 |
| Number of equal steps Includes the top tread; no landing or hollow underside. | n_steps | 4 | |
| Rise per step Height increase of each successive tread. | r_step | m | 0.18 |
| Tread depth Horizontal run per tread. | a_step | m | 0.28 |
| Extra concrete (%) User allowance; 10 means ten percent. | extra_pct | 10 | |
| Bag yield Published QUIKRETE yields; confirm the label for the exact product. | bag_size | 80 lb bag · 0.60 ft³ | |
| Yield per bag Volume of mixed concrete per bag, from your supplier. | yield_custom | m^3 | 0.017 |
| Ready-mix order increment Supplier's volume rounding increment. | order_inc | m^3 | 0.1 |
| Usable load per delivery Usable delivered volume; confirm supplier limits. | truck_cap | m^3 | 6 |
| Include rectangular rebar grid Takeoff only; not reinforcement design. Applies to slabs and footings. | use_grid | true | |
| Clear cover Distance from concrete face to the outer steel surface. | cover | mm | 40 |
| Bar diameter Nominal diameter; one size in both directions. | bar_d | mm | 12 |
| Maximum centre spacing Bars are evenly distributed at no more than this spacing. | pitch | mm | 200 |
| Grid mats per element Each mat has two crossing sets of straight bars. | n_mats | 1 | |
| Extra steel for purchasing (%) Length allowance only; does not detail laps or optimise stock cuts. | steel_pct | 5 | |
| Mean 28-day strength at 20 °C Expected mean compressive strength, not characteristic design strength. Use a consistent cylinder/test basis. | f_28 | MPa | 30 |
| Strength development class CEM I benchmarks only. Blended cements and admixtures need mix-specific calibration. | cement | Normal · s = 0.25 | |
| Calibrated strength coefficient s Dimensionless coefficient fitted to your mix's strength tests. | s_custom | 0.25 | |
| Average concrete curing temperature Constant-temperature planning assumption. Use concrete temperature, not an uncorrected weather forecast. | T_site | °C | 20 |
| Age after pouring Select a calendar age or play the timeline. Results before one equivalent day are withheld. | age | day | 7 |
| Form-release strength target Illustrative default only. Engineer to specify for the form type, self-weight, shoring, and construction loads. | f_strip | MPa | 15 |
| Vehicle-access strength target Illustrative default only. Engineer to specify for slab thickness, subgrade, wheel loads, and concrete test basis. | f_drive | MPa | 25 |
Results
With the default inputs above, the calc gives:
| Result | Value |
|---|---|
| Net concrete | 3.6 m³ |
| Concrete including allowance | 3.96 m³ |
| Ready-mix order | 4 m³ |
| Delivery loads | 1 |
| Whole bags at selected yield | 234 |
| Yield from whole bags | 3.976 m³ |
| Straight bars, all elements and mats | 52 |
| Rebar length incl. purchase allowance | 258.1 m |
| Theoretical rebar mass incl. allowance | 229.2 kg |
| Estimated strength at selected age | 23.36 MPa |
| Equivalent age at 20 °C | 7 day |
| Estimated age to form-release target | 1.97 day |
| Estimated age to vehicle-access target | 9.36 day |
| Strength estimate use | Planning estimate: verify strength before loading or form release |
Checked against sources
Each case below was calculated by this calc and agrees with the value from its source (within the tolerance where one is shown).
QUIKRETE 10 ft × 6 ft × 4 in slab; 80 lb whole bags
Source: QUIKRETE Training Module 3, attached s2 page 11. Published slab volume is 20 ft³. The slide incorrectly rounds 20/0.60 = 33.33 down to 33 bags and 20/0.45 = 44.44 down to 44. The correct purchase counts are 34 and 45 whole bags; the physics and upward rounding are retained. URL: https://www.quikrete.com/dealers/training/presentations/3-mixing-placing-concrete-cement-mixes-training.pdf
Inputs: Length = 3.048 m; Width = 1.829 m; Depth / thickness = 0.1016 m; Extra concrete (%) = 0; Include rectangular rebar grid = no; the others as above.
| Result | Source | This calc |
|---|---|---|
| Net concrete | 0.5663 m³ | 0.5663 m³ |
| Whole bags at selected yield | 34 | 34 |
QUIKRETE 10 ft × 6 ft × 4 in slab; 60 lb whole bags
Source: QUIKRETE Training Module 3, attached s2 page 11. Published slab volume is 20 ft³. The slide incorrectly rounds 20/0.60 = 33.33 down to 33 bags and 20/0.45 = 44.44 down to 44. The correct purchase counts are 34 and 45 whole bags; the physics and upward rounding are retained. URL: https://www.quikrete.com/dealers/training/presentations/3-mixing-placing-concrete-cement-mixes-training.pdf
Inputs: Length = 3.048 m; Width = 1.829 m; Depth / thickness = 0.1016 m; Extra concrete (%) = 0; Bag yield = 60 lb bag · 0.45 ft³; Include rectangular rebar grid = no; the others as above.
| Result | Source | This calc |
|---|---|---|
| Net concrete | 0.5663 m³ | 0.5663 m³ |
| Whole bags at selected yield | 45 | 45 |







Responses