House Electrical Load Schedule: Demand, Breakers & Cables
Build a house load schedule, balance single-phase circuits, and estimate demand, main breaker and supply kVA. Compare editable IEC-style factors with the NEC 220.82 optional-method structure.
This electrical load calculation for a house turns a list of circuit loads into a demand estimate, breaker schedule, cable screening table and supply-capacity estimate. It is intended for engineers, students and homeowners preparing information for a qualified electrical designer. The single-line drawings show the main distribution arrangement and all eleven circuit connections.
Start with the supply arrangement and demand method. The generic IEC-style option supports single phase or a three-phase wye supply. Enter phase-to-neutral voltage, then edit each circuit’s connected electrical input, power factor and demand factor. A zero connected load disables that row. Each row represents one physical circuit: do not combine several branch circuits and use its resulting breaker for all of them. The fixed labels cover common household circuits; a larger installation needs an extended panel schedule.
Individual demand factors reduce loads only for whole-board demand. An additional board simultaneity factor is available when justified, with a default of one to avoid adding unsubstantiated diversity. Heating and cooling can be marked noncoincident. The calculator then checks both operating scenarios after allocating circuits, since the most heavily loaded phase can differ between seasons.
The NEC option implements the NFPA 70, 2023 edition, 220.82 optional-method structure for one 120/240 V split-phase dwelling. Floor-area lighting and general-use receptacle allowance, small-appliance and laundry allowances, and appliance nameplates form the general subtotal. The first block is included fully and the remainder receives the editable demand factor. The applicable heating or cooling term is added afterwards. Counts and factors remain visible and editable in this mode. The worksheet does not claim adoption of the 2026 NEC or local amendments.
Use the load schedule calculator to distinguish connected current, calculated demand and selected protection. Branch breakers use full connected current with the chosen design multiplier, independently of service diversity. NEC kitchen and laundry receptacle rows remain at 20 A and reject overloads. A NEC EV charger retains at least 125% branch sizing even when the discretionary multiplier is lower. The generic main uses the worst phase; the NEC main uses the optional service calculation and a 100 A minimum. This explains how to size a main breaker without simply adding branch-breaker handles. Rounded transformer or supply kVA includes the selected utilization target and growth allowance; confirm an available utility rating.
Generic cable candidates use a named manufacturer’s in-air product ratings with explicit correction and minimum-area inputs. NEC mode requests a listed cable instead. Follow the Cable Size links for each circuit and the main in the method notes to check route length, voltage drop, thermal conditions and protection.
Factors vary by country and installation. This tool does not check neutral harmonics, short-circuit withstand, disconnection, selectivity, earthing, RCD/AFCI requirements or equipment-specific MCA/MOCP. Installation design and work belong to a licensed electrician or other locally qualified person. Check against the standard in force.
How it is calculated
Connected load and generic demand
For each circuit, and , with kVA converted to VA. The generic IEC-style preset is an editable engineering scenario, not an IEC residential demand-factor table. Apply each demand factor , then the separately justified board simultaneity : . If C9/C10 are interlocked, use their larger contribution to the total. In strict terminology the board diversity factor is ; the entered is coincidence/simultaneity. Schneider's demand guide explains this distinction and why local factors differ.
Largest-first allocation places each single-phase circuit on the least-loaded phase. Both HVAC alternatives participate in this physical allocation. With an HVAC interlock, calculate cooling and heating scenarios separately and size the generic main for the largest phase current in either scenario, then apply board simultaneity and growth. The chart shows individual demands before the board factor. In NEC mode it shows connected loads, with 240 V circuits shared across both legs; it does not allocate NEC service demand or calculate a code neutral load. Allocation is a deterministic heuristic, not a guaranteed optimum.
NEC optional-method structure
The NEC 2023, 220.82 worksheet uses eligible floor area at 3 VA/ft² and 1.5 kVA per small-appliance/laundry circuit. These allowances replace actual C1–C4 loads for service calculation; their physical branch currents still use the entered loads. C5–C8 and C11 enter the general nameplate subtotal. Apply the first 10 kVA at 100% and the remainder at 40%, then add the governing HVAC term. The comparison table always displays this separate worksheet; select NEC mode to edit its allowances. The basis is documented by the Truckee and Garden Grove municipal worksheets.
C9 is cooling or heat-pump compressor input, and C10 is resistance or supplemental heat. Compare cooling with 65% resistance heat for fewer than four controlled units, 40% for at least four, or full storage heat. A heat pump with auxiliary heat uses compressor plus 65% auxiliary heat; with compressor lockout, compare compressor with the factored auxiliary load. Corresponding factors are editable. C11 enters at nameplate by default. NEC 2023 220.82(A) permits this calculation instead of Part III; its 220.57 minimum is therefore not silently imported. An optional project EVSE floor is editable, with zero meaning nameplate. Obtain the AHJ’s interpretation and check the adopted edition, especially for EVSE or energy management. The NFPA public record gives the existing 220.82 text as well as Part III 220.57; proposals within that record are not adopted rules. No automatic EMS credit is taken.
Protection, cables and supply capacity
Branch design current uses full connected current and the explicit design multiplier; service demand factors never reduce it. The default 1.25 treats all branch load as continuous. NEC C2–C4 are fixed 20 A kitchen/laundry receptacle circuits under 210.11(C)(1)–(2); a design current above 20 A is rejected, with instructions to split the load across additional physical circuits and update allowance counts. These breakers are not upsized to solve an overload. Weld County's 2023 NEC guide confirms these circuit ratings (pp.3–4).
For C11 identified as EVSE in NEC mode, the branch multiplier is at least 1.25 regardless of the discretionary input. This enforces ordinary NEC 2023 625.41 continuous-duty protection independently of the 220.82 service worksheet: 48 A charging requires at least 60 A protection, matching Tesla's published table. Reductions for special continuous-duty assemblies or managed charging are not modeled. Other rows select the next rating in the product-based assortment, with a 15 A floor for NEC C1. Equipment-specific maximum protection and MCA/MOCP remain separate. The main uses the selected demand method, growth and minimum service rating.
The generic thermal screen requires corrected manufacturer ampacity and the entered minimum area. Manufacturer Eland NYY-J product ratings at 30 °C in air are attached as s2, pp.5–6. Branches use the 3-core subset; the three-phase main uses the 5-core subset, available here only through 25 mm². No standard ampacity table is reproduced. The correction factor must describe the actual installation. The schedule's Base amp. column is the required uncorrected ampacity. NEC mode displays required base ampacity equal to the breaker current and asks for an eligible listed cable; it does not recommend NYY-J or apply the generic correction.
Generic supply phase-capacity equivalent is ; NEC uses its calculated VA including growth. Divide by target utilization and round upward in the selected kVA increment. This is a planning capacity, not a verified transformer product or its protection design.
Check each cable in the published Cable Size calculator
Carry the circuit current, candidate breaker, conductor size, actual voltage and one-way route length to its cable check. For the main, carry the design current and selected main rating. Confirm operating temperature, installation thermal paths, voltage drop, fault-loop/disconnection and manufacturer protection data. The links target the currently published catalog entry.
- C1: Lighting / general outlets — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C2: Kitchen small appliance 1 — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C3: Kitchen small appliance 2 — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C4: Laundry receptacle — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C5: Cooker / range — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C6: Water heater — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C7: Dryer / fixed appliance — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C8: Dishwasher / fixed appliance — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C9: Cooling / heat-pump compressor — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C10: Heating / auxiliary heat — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- C11: EVSE / other fixed load — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
- Main feeder — Cable Size (https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/)
Assumptions
- Default house: eleven available physical circuit slots, nine enabled; generic three-phase 230 V phase to neutral, unity power factors except C9 at 0.9. Powers and demand factors are explicit hypothetical design inputs, not measured usage or country-prescribed values.
- All generic rows are phase-to-neutral single-phase circuits. Balanced three-phase appliances and line-to-line generic loads need a separate model. Changing method does not claim that the physical installation has been rewired.
- NEC mode is fixed to 120/240 V split phase: C1–C4 and C8 are 120 V; C5–C7 and C9–C11 are 240 V. This fixed connection template must match actual equipment. Optional-method eligibility assumes one dwelling, a single qualifying service/feeder, and at least 100 A.
- C1 is one lighting/general-use circuit slot, not an entire real house lighting/receptacle layout. The service floor-area allowance covers general use independently. More circuits than these eleven slots require a larger installation schedule; a zero slot is omitted rather than treated as a minimum mandatory circuit.
- Sinusoidal RMS steady-state loads with nonleading power factor. Arithmetic sums of apparent powers are conservative where power factors differ. No motor starting or harmonic neutral heating is modeled.
- Generic cable correction 0.8, minimum branch area 2.5 mm² and main area 4 mm² are explicit project assumptions. Obtain local minimum areas and applicable rating/correction procedures. Manufacturer nominal metric sizes retain their product names when display units change.
- Growth multiplier 1, utilization 0.8 and 5 kVA rounding are editable planning choices. A main smaller than a branch breaker does not establish selectivity or a guarantee that simultaneous nameplate loads can run.
- Both drawings are conceptual single lines: every enabled circuit remains individually protected. Phase groups in the first drawing are not additional calculated feeder breakers. Earthing, neutral conductors, RCDs and auxiliary devices are omitted for clarity.
- In NEC mode the fixed 20 A C2–C4 rows cannot represent larger dedicated appliance circuits. Add physical circuits and revise the kitchen/laundry service allowance counts when splitting a load. C11 EVSE branch protection always uses at least 125% of connected current, including when a lower discretionary multiplier is entered.
Where it applies
Rules/source review date: 2026-10-26. Generic coordination follows the overload-screen principle associated with IEC 60364-4-43:2023, edition 4.0; the full device criterion, breaking capacity and installation requirements are not established by this screen. The optional-method basis is NFPA 70 (NEC), 2023 edition, 220.82, using nameplate EVSE load unless the user specifies a project minimum. NEC 2026 is now published; this tool deliberately identifies its 2023 basis and does not claim the editions are interchangeable. Check against the standard in force and the authority having jurisdiction.
A licensed electrician or other locally qualified electrical designer must design the installation; installation work belongs to qualified persons. This calculator supports learning and preliminary schedules, not permit approval.
Apart from the fixed NEC kitchen/laundry breaker ratings and ordinary EVSE branch minimum enforced here, no checks are made for neutral sizing, triplen harmonics, earthing/bonding, RCD/AFCI/GFCI requirements, selectivity, fault breaking capacity, disconnection time, short-circuit withstand, voltage drop, equipment minimum/maximum circuit protection or conductor terminal limits. In NEC mode confirm listed cable ampacity, small-conductor restrictions, termination ratings, minimum circuits and appliance/motor-specific articles. Special equipment can invalidate an ordinary next-breaker selection. The tool does not support reducing EVSE branch protection below the ordinary 125% minimum through a 100%-rated assembly or energy-management exception.
A positive cable candidate means only that the modeled ampacity and area screen passes. It is not authorization to install that cable. A zero candidate means off or outside the source subset, distinguished in the status text. Five-core source data above 25 mm² are not extrapolated.
The Truckee reference retains its published 7.0 kVA EVSE nameplate and reproduces 29.52 kVA. A separate sensitivity case adds an explicit 7.2 kVA project floor and obtains 29.60 kVA; that case is not a correction of the published optional calculation or a claim that Part III 220.57 governs it. The apartment-block reference verifies only the demand arithmetic, not house branch circuit design.
References
- Town of Truckee, Residential Electrical Load Worksheet, 2025 California code context, worked example p.2 (attached s1 link): https://www.townoftruckee.gov/DocumentCenter/View/2239
- City of Garden Grove, Residential Electrical Load Calculation, optional method Article 220.82, revised January 2026: https://ggcity.org/sites/default/files/filefield_paths/residential-load-calcs_0.pdf
- Schneider Electric, Electrical Installation Guide, Estimation of actual maximum kVA demand (attached s3): https://www.electrical-installation.org/enwiki/Estimation_of_actual_maximum_kVA_demand
- Schneider Electric, Practical values for a protective scheme (attached s4): https://www.electrical-installation.org/enwiki/Practical_values_for_a_protective_scheme
- Eland Cables, NYY-J PVC 0.6/1 kV product datasheet, attached s2 pp.5–6: https://www.elandcables.com/media/ohehbamm/nyy-j-pvc-0-6-1kv-power-cable-datasheet.pdf
- Schneider Electric, Acti9 iC60N product rating choices, attached s5: https://www.se.com/eg/en/product/A9F77163/miniature-circuitbreaker-acti9-ic60n-1p-63-a-c-curve-6000-a-iec-608981-10-ka-iec-609472/
- Schneider Electric, ComPacT NSX User Guide, current range, attached s9: https://productinfo.se.com/compactnsxuserguide/viewer?docidentity=D-SE-0068738&extension=xml&lang=en&manualidentity=UserGuidePacTSeriesComPacTNSXCircui-67530380
- Eaton, Residential and light commercial loadcenters and circuit breakers, CA08100002E, November 2022, product current assortments (attached s6): https://www.eaton.com/content/dam/eaton/products/low-voltage-power-distribution-controls-systems/loadcenters-and-circuit-breakers-v1-t1-ca08100002e.pdf
- NFPA public committee record, existing NEC 2023 220.82 optional calculation and Part III 220.57 EVSE minimum, attached s7. Proposals within the record are not adopted rules: https://docinfofiles.nfpa.org/files/AboutTheCodes/70/70_A2025_NEC_P02_FD_PIResponses.pdf
- IEC 60364-4-43:2023, edition 4.0, overcurrent protection scope, attached s8: https://webstore.iec.ch/en/publication/28432
- NFPA 70 official edition status (2026 currently published): https://www.nfpa.org/codes-and-standards/nfpa-70-development/70
- WiredWhite Cable Size and Voltage Drop Calculator, published catalog entry: https://staging.wiredwhite.com/calcs/cable-size-and-voltage-drop-calculator/
- Weld County Building Inspection Division, Basic Requirements for Wiring a Single Family Dwelling, revised July 2024, NEC 2023 guide, pp.3–4; attached s12 link: https://www.weld.gov/files/sharedassets/public/v/5/departments/building/documents/handouts/residential/basic-wiring-requirements.pdf
- Tesla, Wall Connector support, Vehicle Charging Speeds table, 48 A maximum output / 60 A breaker; attached s10 link: https://www.tesla.com/support/charging/wall-connector
- NFPA public committee record, existing 2023 625.41 ordinary EVSE continuous-duty protection. Proposed exceptions are not treated as adopted rules; attached s11: https://docinfofiles.nfpa.org/files/AboutTheCodes/70/70_A2025_NEC_P12_FD_PIResponses.pdf
Inputs
| Input | Symbol | Unit | Default |
|---|---|---|---|
| Demand method Generic factors are design assumptions, not an IEC residential demand table. NEC mode is a 120/240 V split-phase dwelling worksheet; confirm local adoption. | method | Generic IEC-style · editable factors | |
| Supply arrangement | supply | Three phase wye, line + neutral | |
| Phase-to-neutral voltage All generic circuit rows are single phase, phase to neutral. Three-phase line voltage is √3 times this value. | U_phase | V | 230 |
| Board simultaneity factor Multiplies the sum of the individual circuit demands. Keep 1 unless additional whole-board diversity is justified; avoid counting diversity twice. | k_s | 1 | |
| Heating and cooling cannot run together When true, only the larger circuit demand of C9 and C10 contributes to board demand. Both circuits retain their full branch current. | exclusive_hvac | true | |
| Main supply design multiplier An explicit allowance above calculated demand, e.g. 1.2 for 20% growth. Not a mandatory code demand factor. | reserve | 1 | |
| Branch design-current multiplier Applied to full connected current, independently of service demand. Default 1.25 treats the whole branch load as continuous. NEC C2–C4 remain fixed at 20 A and reject overloads; NEC C11 EVSE always retains at least 1.25. Equipment-specific MCA/MOCP still governs other rows. | continuous_multiplier | 1.25 | |
| Combined cable ampacity correction Generic NYY-J in-air candidate only: enter the product of applicable correction factors for temperature, grouping and installation. The 0.8 default is an explicit design assumption, not a standard value. | cable_factor | 0.8 | |
| Minimum main rating Local or utility minimum. NEC mode also applies a 100 A dwelling service minimum. | main_floor | A | 25 |
| Maximum target supply utilization Required transformer/supply kVA is the phase-capacity equivalent divided by this ratio. 0.8 is a planning choice, not a transformer standard. | transformer_utilization | 0.8 | |
| Supply rating rounding increment Rounds required kVA upward in your chosen increment. The rounded result is a planning rating; verify a utility/manufacturer size. | transformer_step | kVA | 5 |
| Dwelling floor area Eligible floor area only; excludes open porches, garages and unfinished areas not adaptable for use. | area | m^2 | 180 |
| General lighting unit load NEC 2023 basis: 3 VA/ft² includes general-use receptacles. This replaces actual C1 connected load for service demand. | lighting_density | VA/ft^2 | 3 |
| Small-appliance circuits counted Service allowance count. C2/C3 are two physical schedule slots, not all circuits when this count exceeds two. | n_small | 2 | |
| Laundry circuits counted | n_laundry | 1 | |
| Allowance per small-appliance/laundry circuit | circuit_allowance | kVA | 1.5 |
| General load block at 100% | full_block | kVA | 10 |
| General load remainder factor | remainder_factor | 0.4 | |
| Heating calculation option C9 is cooling or heat-pump compressor input; C10 is resistance or supplemental heat. Use electrical input, not thermal output. | heat_kind | Resistance heat · fewer than 4 controlled units | |
| Resistance / auxiliary heat factor Default 0.65 for fewer than four controlled resistance units, or supplemental heat. Four-or-more mode uses its separate editable factor. | heat_factor | 0.65 | |
| Four-or-more heating-unit factor | four_heat_factor | 0.4 | |
| Compressor is locked out during auxiliary heat If true, compare compressor with factored auxiliary heat; otherwise add compressor plus factored auxiliary heat. | hp_interlock | false | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P1 | kW | 0.6 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf1 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d1 | 0.9 | |
| Connected electrical input One physical circuit; zero omits this row. In NEC mode this is fixed at 20 A: reduce or split any load exceeding its design-current limit across additional physical 20 A circuits. Update the allowance count and full panel schedule. | P2 | kW | 1.5 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf2 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d2 | 0.6 | |
| Connected electrical input One physical circuit; zero omits this row. In NEC mode this is fixed at 20 A: reduce or split any load exceeding its design-current limit across additional physical 20 A circuits. Update the allowance count and full panel schedule. | P3 | kW | 1.5 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf3 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d3 | 0.6 | |
| Connected electrical input One physical circuit; zero omits this row. In NEC mode this is fixed at 20 A: reduce or split any load exceeding its design-current limit across additional physical 20 A circuits. Update the allowance count and full panel schedule. | P4 | kW | 1.5 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf4 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d4 | 0.7 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P5 | kW | 7.2 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf5 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d5 | 0.6 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P6 | kW | 3 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf6 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d6 | 0.8 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P7 | kW | 2.5 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf7 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d7 | 0.6 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P8 | kW | 1.2 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf8 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d8 | 0.7 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P9 | kW | 3.2 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf9 | 0.9 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d9 | 1 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P10 | kW | 0 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf10 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d10 | 1 | |
| Connected electrical input One actual circuit per row. Enter zero to omit it. Do not combine several physical circuits into one breaker recommendation. | P11 | kW | 0 |
| Power factor Electrical real power divided by apparent power. Use nameplate input; mechanical/thermal output is not input power. | pf11 | 1 | |
| Circuit demand factor Applied to this circuit for board demand only; its breaker is sized from full connected load. | d11 | 1 | |
| Minimum branch conductor area Project minimum applied to every generic circuit. Check local minimum sizes; thermal ampacity alone does not determine permitted conductor size. | A_min_branch | mm^2 | 2.5 |
| Minimum main conductor area | A_min_main | mm^2 | 4 |
| C11 is an EV charger Marks C11 as EVSE: NEC branch sizing retains at least 125% independently of the user multiplier. Service demand uses nameplate unless an optional project floor is entered. | other_is_ev | true | |
| Optional project minimum per installed EVSE Zero uses EVSE nameplate under the modeled 2023 220.82(B) optional structure. Part III 220.57 states 7.2 kVA, but 220.82(A) replaces Part III; do not silently transfer that requirement. Enter a project/AHJ minimum only when justified. | ev_floor | kVA | 0 |
Results
With the default inputs above, the calc gives:
| Result | Value |
|---|---|
| Connected load | 22.56 kVA |
| Calculated demand | 16.01 kVA |
| Main design current | 23.7 A |
| Candidate main breaker | 25 A |
| Minimum supply planning capacity | 20.42 kVA |
| Rounded supply / transformer | 25 kVA |
Checked against sources
Each case below was calculated by this calc and agrees with the value from its source (within the tolerance where one is shown).
Truckee optional-method worked example · nameplate EVSE
Source: Town of Truckee Residential Electrical Load Worksheet, worked example p.2: 2800 ft², three allowance circuits, range 12 kVA, water heater 3, dryer 5, dishwasher 1.5, EVSE 7, cooling 6.96; published service demand 29.52 kVA and 123 A. The modeled NEC 2023 220.82(B) optional structure uses these nameplates. Its replacement of Part III is explicit in 220.82(A), so a Part III EVSE minimum is not silently transferred. https://www.townoftruckee.gov/DocumentCenter/View/2239
Inputs: Demand method = NEC 2023 · 220.82 optional structure; Dwelling floor area = 260.1 m²; Connected electrical input = 12 kW; Connected electrical input = 5 kW; Connected electrical input = 1.5 kW; Connected electrical input = 6.96 kW; Power factor = 1; Connected electrical input = 7 kW; the others as above.
| Result | Source | This calc |
|---|---|---|
| NEC floor-area allowance | 8.4 kVA | 8.4 kVA |
| NEC general connected allowance | 41.4 kVA | 41.4 kVA |
| NEC general demand | 22.56 kVA | 22.56 kVA |
| Calculated demand | 29.52 kVA | 29.52 kVA |
| Main design current | 123 A | 123 A |
Truckee example · explicit 7.2 kVA project EVSE floor
Source: Sensitivity calculation using Truckee's independent worked-example inputs and an explicit 7.2 kVA project EVSE floor. The 7.2 kVA value appears in Part III NEC 2023 220.57, as shown in NFPA public record s7, but 220.82(A) permits the optional calculation instead of Part III. This case is a user-selected project allowance, not a mandatory optional-method rule or a correction of Truckee. Increasing its 7.0 kVA EVSE entry by 0.2 kVA adds 0.08 kVA after the remainder factor: 29.60 kVA. https://www.townoftruckee.gov/DocumentCenter/View/2239 ; https://docinfofiles.nfpa.org/files/AboutTheCodes/70/70_A2025_NEC_P02_FD_PIResponses.pdf
Inputs: Demand method = NEC 2023 · 220.82 optional structure; Dwelling floor area = 260.1 m²; Connected electrical input = 12 kW; Connected electrical input = 5 kW; Connected electrical input = 1.5 kW; Connected electrical input = 6.96 kW; Power factor = 1; Connected electrical input = 7 kW; Optional project minimum per installed EVSE = 7.2 kVA; the others as above.
| Result | Source | This calc |
|---|---|---|
| NEC general connected allowance | 41.6 kVA | 41.6 kVA |
| Calculated demand | 29.6 kVA | 29.6 kVA |
| Main design current | 123.3 A | 123.3 A |
| Candidate main breaker | 125 A | 125 A |
Eland 3-core 1.5 mm² in-air product rating
Source: Eland NYY-J product datasheet, attached s2 p.5: published 3-core 1.5 mm² rating is 18 A in air. A 16 A test breaker requests the smallest product passing this manufacturer's rating; this does not verify voltage drop or local minimum size. https://www.elandcables.com/media/ohehbamm/nyy-j-pvc-0-6-1kv-power-cable-datasheet.pdf
Inputs: Supply arrangement = Single phase, line + neutral; Branch design-current multiplier = 1; Combined cable ampacity correction = 1; Minimum branch conductor area = 1.5 mm²; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Circuit demand factor = 1; Connected electrical input = 3.68 kW; the others as above.
| Result | Source | This calc |
|---|---|---|
| Generic circuit cable cross-sections [1] | 1.5 mm² | 1.5 mm² |
| Generic corrected cable ampacity [1] | 18 A | 18 A |
Eland 3-core 2.5 mm² in-air product rating
Source: Eland NYY-J product datasheet, attached s2 p.5: published 3-core 2.5 mm² in-air rating is 25 A; 1.5 mm² is rated 18 A and fails a 20 A breaker. These are manufacturer product ratings, not a copied standard table. https://www.elandcables.com/media/ohehbamm/nyy-j-pvc-0-6-1kv-power-cable-datasheet.pdf
Inputs: Supply arrangement = Single phase, line + neutral; Branch design-current multiplier = 1; Combined cable ampacity correction = 1; Minimum branch conductor area = 1.5 mm²; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Circuit demand factor = 1; Connected electrical input = 4.6 kW; the others as above.
| Result | Source | This calc |
|---|---|---|
| Generic circuit cable cross-sections [1] | 2.5 mm² | 2.5 mm² |
| Generic corrected cable ampacity [1] | 25 A | 25 A |
Schneider apartment-block demand arithmetic
Source: Schneider Electric Electrical Installation Guide, Estimation of actual maximum kVA demand, example of 25 consumers: installed floor totals 36 + 24 + 30 + 36 + 24 = 150 kVA, and 0.46 simultaneity gives 69 kVA. Rows represent source floor groups for this arithmetic check only; this is not a valid household branch installation recommendation. https://www.electrical-installation.org/enwiki/Estimation_of_actual_maximum_kVA_demand
Inputs: Connected electrical input = 36 kW; Connected electrical input = 24 kW; Connected electrical input = 30 kW; Connected electrical input = 36 kW; Connected electrical input = 24 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Connected electrical input = 0 kW; Board simultaneity factor = 0.46; Circuit demand factor = 1; Circuit demand factor = 1; Circuit demand factor = 1; Circuit demand factor = 1; Circuit demand factor = 1; the others as above.
| Result | Source | This calc |
|---|---|---|
| Connected load | 150 kVA | 150 kVA |
| Calculated demand | 69 kVA | 69 kVA |
NEC overloaded kitchen/laundry rows retain fixed 20 A protection
Source: Weld County, Basic Requirements for Wiring a Single Family Dwelling, revised July 2024, NEC 2023 guide, p.3 kitchen circuits and p.4 laundry circuit: these dedicated receptacle circuits are 20 A. This deliberately overloaded input tests that fixed protection never increases; the overload must be rejected by the separate input condition and is not an acceptable installation. https://www.weld.gov/files/sharedassets/public/v/5/departments/building/documents/handouts/residential/basic-wiring-requirements.pdf
Inputs: Demand method = NEC 2023 · 220.82 optional structure; Connected electrical input = 3 kW; Connected electrical input = 3 kW; Connected electrical input = 3 kW; the others as above.
| Result | Source | This calc |
|---|---|---|
| Candidate circuit breaker ratings [2] | 20 A | 20 A |
| Candidate circuit breaker ratings [3] | 20 A | 20 A |
| Candidate circuit breaker ratings [4] | 20 A | 20 A |
Tesla 48 A charging requires 60 A breaker despite a 1.0 user multiplier
Source: Tesla Wall Connector support, Vehicle Charging Speeds technical table: maximum output 48 A on a 60 A breaker at 240 V. The source rounds power to 11.5 kW; the test enters 11.52 kW = 240 V × 48 A to preserve its exact current. The discretionary branch multiplier is deliberately 1.0 to verify that the ordinary NEC EVSE 125% branch minimum remains enforced. https://www.tesla.com/support/charging/wall-connector
Inputs: Demand method = NEC 2023 · 220.82 optional structure; Connected electrical input = 11.52 kW; Branch design-current multiplier = 1; the others as above.
| Result | Source | This calc |
|---|---|---|
| Connected branch current [11] | 48 A | 48 A |
| Branch design current before rating selection [11] | 60 A | 60 A |
| Candidate circuit breaker ratings [11] | 60 A | 60 A |
Related Resources
Related courses
IEC Electrical Schematics and Industrial Control Panels
5
Original price was: 42 €.21 €Current price is: 21 €.
Basic Electrical Controls & Diagram Reading
7
Original price was: 32 €.18 €Current price is: 18 €.
Modeling Electrical Motor Faults with FEM Simulation using ANSYS MAXWELL
3
Original price was: 50 €.15 €Current price is: 15 €.







Responses